MOUNTING AND ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
June 1, 2024 as of 7:25 PM today The New 15 MVA Power transformer has been properly positioned into its mounting platform and the area has been cleared of debris. Initial testing has been made and the result is positive. Working crews are now preparing the...
PARALLEL ACTIVITIES WHILE THE 15 MVA IS BEING PREPARED FOR ENERGIZATION AT DAO SUBSTATION
June 1, 2024, Saturday Making use that power is out at Dao Substation, the construction crew conducted their own activities accomplishing the following: • Relocation of 3-Phase line at Sitio Utod, San Miguel, Dumalag (FB Complain) • Insertion of pole at Barangay San...
POST SCHEDULED POWER INTERRUPTION REPORT
June 1, 2024, Saturday Reason: The National Grid Corporation od the Philippines (NGCP) will facilitate the replacement of wooden poles along the along 69KV Panitan-Sara line section Areas affected and time: As scheduled: from 5:00 AM to 6:00 PM In actual: from 5:09 AM...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 11
May 28-29, 2024, Friday and Saturday #TeamBobongSaron BT 11 Team Members: J Saron, R Fabella, JD Batuampo and M Deocampo Accomplished: 1. Pull out of Capiztahan billboard at Gaisano Boulevard, Roxas City 2. Replacement of rotten of pole at Dorado Subdivision, Inzo...