MOUNTING AND ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
June 1, 2024 as of 9:14 PM today The work at Dao Substation continue as the crew are now laying down the cables for the interconnection of the 15 MVA power transformer. This is 15 hours of straight work already in time for the eventual energization by tomorrow and the...
MOUNTING AND ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
June 1, 2024 as of 7:25 PM today The New 15 MVA Power transformer has been properly positioned into its mounting platform and the area has been cleared of debris. Initial testing has been made and the result is positive. Working crews are now preparing the...
PARALLEL ACTIVITIES WHILE THE 15 MVA IS BEING PREPARED FOR ENERGIZATION AT DAO SUBSTATION
June 1, 2024, Saturday Making use that power is out at Dao Substation, the construction crew conducted their own activities accomplishing the following: • Relocation of 3-Phase line at Sitio Utod, San Miguel, Dumalag (FB Complain) • Insertion of pole at Barangay San...
PREPARATORY ACTIVITY FOR THE ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
June 1, 2024, Saturday Accomplished: 1. Installation of 1 span 3phase line @ Dao substation to energize Dao from Feeder 4 Panitan Substation via looping connection 2. Connection of jumper from 13.2 to 69 kV at bypass road Barangay Amaga, Sigma to energize Dao from...