SCHEDULED POWER INTERRUPTION

SCHEDULED POWER INTERRUPTION

February 24, 2024, Saturday 8:00 sang aga tubtob 4:00 sang hapon Ang CAPELCO mapatigayon sang Line Maintenance kag Clearing. LUGAR NGA APEKTADO: -Brgy. Bonga -Sitio Arellano kag Cambuyayao -Brgy. Pawa -Brgy. Buntod -Brgy. Jamul-awon -Brgy. Navitas -porsyon sang Brgy....
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 7

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 7

February 19, 2024, Monday #TeamRamilDistura BT7 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog Accomplished: 1. Replacement of 2 units of rotten pole at Barangay Agloway, Panitan 2. Pull out of temporary 37.5 KVA transformer at Barangay...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT1

CONSOLIDATED TEAM ACCOMPLISHMENTS BT1

February 17-19, 2024, Saturday to Monday #TeamTamtamDangan BT1 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes Accomplished: 1. Replacement of rotten pole at Barangay Poblacion Ilaya, Panitan 2. Replacement of defective 37.5 KVA transformer at...