CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8
July 15-19, 2024, Monday to Friday #TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog Accomplished: 1. Rehabilitation of lines from duplex # 6 to secondary line extension and transfer metering at Barangay Agsilab, Sapian. 2....
POST SCHEDULED POWER INTERRUPTION REPORT
July 20, 2024, Saturday As scheduled: From 6:00 AM to 10:00 AM In actual: Chronology of power restoration • 6:00 AM opened Feeder 1 • 6:03 AM Closed blade disconnect switch at Barangay Bago and opened jumper at Calitan 3-phase line • 9:07 AM opened Feeder 1 Areas...
SCHEDULED EMERGENCY POWER INTERRUPTION
July 21, 2024, Sunday, As scheduled: From 4:00 AM to 5:00 AM In actual; From 4:06 AM to 4:33 AM Reason: Hotspot correction of Air Break Switch (ABS) at Lawaan Substation Areas affected: Whole of Roxas City except the Barangays of Adlawan, Liong, Loctugan, Bago and...
CONTINUED HOUSEWIRING OF SEMA BENEFICIARIES
July 18, 2024, Bilao, Sapian The installation of housewiring to qualified beneficiaries of the Socialized Energization of Marginalized Applicants (SEMA) for electric service connection continued as a number of new households had their houses wired. The students doing...