POST EMERGENCY POWER INTERRUPTION REPORT
July 10, 2024, Wednesday Due to bad weather condition and technical problem in the distribution lines causing line faults, a number of emergency power interruptions occurred in different areas in Capiz within the territorial responsibilities of various area offices....
SCHEDULED POWER INTERRUPTION
HULYO 12, 2024 (Biyernes nga adlaw)Alas 8:30 sang aga tubtob Alas 5:00 sang hapon.Ang CAPELCO magapatigayon sang Line Clearing kag Maintenance.LUGAR NGA APEKTADO: Barangay Sta. Fe, Casanayan, San Ramon, Balogo kag Dayhagan, Pilar.Gilayon man nga ibalik ang kuryente sa...
PARALLEL ACTIVITIES DURING THE SCHEDULED POWER INTERRUPTION
July 9, 2024, Tuesday Accomplished: 1. Relocation of pole at Gabuan Roxas City 2. Replacement of Rotten Crossarm at Cals Lawaan Roxas City 3. Replacement of Damaged Pole at Banica Roxas City 4. Switching of breaker at Lawaan Substation 5. Replacement of Rotten...
POST SCHEDULED POWER INTERRUPTION REPORT
July 9, 2024, Tuesday As scheduled: From 4:00 AM to 8:00 AM Reason: NGCP’S De-energization of CAPELCO Feeders (69KV Panitan-Roxas Transmission Line and Timpas Transformer TR1) to facilitate hotspot correction Areas affected: • Whole of Roxas City except Barangay...