CONSOLIDATED REPORT OF EMERGENCY POWER INTERRUPTION
June 5, 2024, various times and different areas affected Mambusao Area Office Disconnected primary line at Barangay Agmabulong, Jamindan Intrusion of gecko at Mianay, Sigma Damaged line side of cut-out Toppled bamboo into the distribution line at Oyong...
POST SCHEDULED POWER INTERRUPTION REPORT
June 5, 2024, Wednesday As scheduled: From 5:00 AM to 6:30 AM In actual: From 5:01 AM to 6:06 AM Purpose: Reconfiguration of Feeder 7R at Lawaan Substation. Affected areas: Feeder 7R – Pueblo De Panay, with Robinsons and Roxas City PNP. Feeder 8R – Barangay...
ANG MALAIN NGA PANAHON ANG GINTUNAAN SANG MALAPNAGON NGA BROWNOUT
Hunyo 4, 2024, Martes nga Adlaw Suno sa impormasyon nga ginpaabot sang mga Area Offices sa Segundo Distrito, masyado kabaskog sang hangin nga may dala nga ulan ang nangin rason sa likod sang malapnagon nga emergency power interruption. Indi nga mga hitabo wala sa aton...
PARALLEL ACTIVITIES WHILE THE 15 MVA IS BEING PREPARED FOR ENERGIZATION AT DAO SUBSTATION
June 2, 2024, Sunday CAPELCO CONSTRUCTION CREWS Accomplished: 1. Relocation of 2 poles and rehabilitation of kilowatt hour meters at Sitio Ayuyan, Barangay Sto. Angel, Dumalag 2. Replacement of rotten pole at Barangay Angub, Cuartero (Double circuit) and...