COMPOSITE TEAM ACCOMPLISHMENTS

COMPOSITE TEAM ACCOMPLISHMENTS

May 24, 2024, Friday Composite Team is made up of newly-graduated trainee lineworkers Team Members: J Degones, S Dela Torre, M Umiten and JP Hachuela Accomplished: Continued work at Barangay Gabuan, Roxas City pole and line...
POST SCHEDULED POWER INTERRUPTION REPORT

POST SCHEDULED POWER INTERRUPTION REPORT

May 24, 2024, Friday As scheduled: From 5:00 AM to 8:00 AM In Actual: From 5:08 AM to 8:37 AM The delay was largely caused by rain that stalled the required testing before the re-energization Areas Affected: Feeder 2 – Municipality of Pontevedra except those connected...
POST EMERGENCY POWER INTERRUPTION REPORT

POST EMERGENCY POWER INTERRUPTION REPORT

May 23-24, 2024, around 9:17 PM to 12:33 AM UPDATE:Feeder D3 normalized at 12:33 AMPlease be advised that there is an emergency tripping off of Feeder D3 connecting the Municipalities of Cuartero, Dumarao and portion of Dao to Dao Substation.Our maintenance personnel...