CONSOLIDATED TEAM ACCOMPLISHMENTS BT 9
#TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura Accomplished: 1. Replacement of rotten overhead pole 2. Replacement polymer/suspension insulator at Barangay Timpas, Panitan to Barangay Malapad Cogon, Sigma 3....

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8
#TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog Accomplished: 1. Digging 4 holes at Sitio Ilawod, Pangpang Norte, Mambusao 2. Pull out of 37.5 KVA transformer at Barangay Tinaytayan, Dumarao 3. Installation of 37.5 KVA...

CAPELCO PARTICIPATED IN THE ROAD CLEARING CONFERENCE
DILG Conference Room, DILG Provincial Office, Roxas City An inter-agency conference was convened by the Department of Interior and Local Government (DILG) to vigorously push the campaign for road clearing as contained in DILG Memorandum Circular 2024-053 entitled...

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 11
#TeamBobongSaron BT 11 Team Members: J Saron, R Fabella, JD Batuampo and M Deocampo Accomplished: Replacement of rotten pole and continuing rehabilitation of kilowatt hour meters at Barangay Cogon, Roxas City

AREA OFFICE MAINTENANCE ACTIVITY
Mambusao Area Office (MAO) #TeamMAOMaintenance Team: J. Adio, J. Lacorte and NJ Miguel Accomplished: Replacement of 2 units of rotten poles at Sitio Malonoy, Barangay Agambulong, Jamindan
Other News
TOOLBOX MEETING WITH NGCP, CONTRACTOR AND CAPELCO ENGINEERS
Agenda: Sequence of activities prior to the moving, installing and energization of 15 MVA power...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 11
#TeamBobongSaron BT 11 Team Members: J Saron, R Fabella, JD Batuampo and M Deocampo Accomplished:...
POST EMERGENCY POWER INTERRUPTION REPORT
Areas affected: Portion of Barangay Barra, Roxas City Reason: Toppled trees into the distribution...
ADVANCED FIRST FRIDAY MASS
Rev. Fr. Rey Villanoy celebrated the Holy Eucharist held in advance that the regular Friday Mass...
ENERGIZATION OF 15 MVA POWER TRANSFORMER FOR DAO SUBSTATION
The energization of the 15 MVA power transformer at Dao Substation will require a total for 36...