PARALLEL TECHNICAL ACTIVITIES DURING THE SCHEDULED POWER INTERRUPTION
Taking time that power is out due to the Preventive Maintenance Servicing of Panitan Substation, CAPELCO’s construction crew and the maintenance crew conducted parallel activities to make use of the time that power is out. Accomplished: 1. Replacement of rotten pole...
POST EMERGENCY POWER INTERRUPTION REPORT
The sporadic and emergency power interruptions continues and our maintenance crew are so busy responding to all of these complaints. Again, not all of the emergency power interruption have been reported here but they are being addressed by our maintenance team who are...
COMPOSITE TEAM ACCOMPLISHMENTS
Composite Team is made up of newly-graduated trainee lineworkers Team Members: J Degones, S Dela Torre, M Umiten and JP Hachuela Accomplished: Continued work at Barangay Gabuan, Roxas City pole and line relocation
FOURTH MONTHLY MEETING FOR 2024 OF MANAGERS, SUPERVISORS AND SECTION HEADS WITH ACTING GENERAL MANAGER
We are experiencing a lot of challenges but we are doing our best to solve them. It is just a question of working together so that we can address real and felt complaints of our member-consumer-owners (MCOs). This is the core of the message of Acting General Manager...
POST SCHEDULED POWER INTERRUPTION REPORT
As scheduled: From 5:00 AM to 8:00 AM In Actual: From 5:08 AM to 8:37 AM The delay was largely caused by rain that stalled the required testing before the re-energization Areas Affected: Feeder 2 – Municipality of Pontevedra except those connected at President Roxas...
Other News
MOUNTING AND ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
The work at Dao Substation continue as the crew are now laying down the cables for the...
MOUNTING AND ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
The New 15 MVA Power transformer has been properly positioned into its mounting platform and the...
PARALLEL ACTIVITIES WHILE THE 15 MVA IS BEING PREPARED FOR ENERGIZATION AT DAO SUBSTATION
Making use that power is out at Dao Substation, the construction crew conducted their own...
PREPARATORY ACTIVITY FOR THE ENERGIZATION OF 15 MVA POWER TRANSFORMER AT DAO SUBSTATION
Accomplished: 1. Installation of 1 span 3phase line @ Dao substation to energize Dao from Feeder 4...
POST SCHEDULED POWER INTERRUPTION REPORT
Reason: The National Grid Corporation od the Philippines (NGCP) will facilitate the replacement of...