From 8:30 AM to 5:00 PM Areas affected: Barangay Matagnop, Malonoy, Agtanguay, Daplas, Ilas Sur, Ilas Norte aand Centro, Dao. Accomplished: Line clearing operation Working Crew: #NLBEnterprises – Line clearing contractor

From 8:30 AM to 5:00 PM Areas affected: Barangay Matagnop, Malonoy, Agtanguay, Daplas, Ilas Sur, Ilas Norte aand Centro, Dao. Accomplished: Line clearing operation Working Crew: #NLBEnterprises – Line clearing contractor
New Road, Barangay Banica, Roxas City Work Done: Installation of Blade Disconnect Switch in order to address recurring and multiple line trippings of 4R Feederline #TeamGeraldCondino BT 10 Team Members: G Condino, C Daliva, NM Distura, M Umiten and A...
Barangay Monteflor, Pilar Power out: 1:00 AM Power restored: 9:30 AM Cause: Disconnected 3-span of single-phase line hit by toppled Mahogany tree Responding Crew: #TeamPRAOMaintenance and BAPA Crew Team Leader: B Dellota Team Members: J Paderes, N Tumlos, J Dorado...
#TeamArlanDangan ML 2 Team Members: A Dangan, E Dublado, R Delfin, J Escalada, N Estorque and L Acejo Accomplished: 1. Line clearing at Sitio Ilaya, Barangay Lanot, Roxas City 2. Line clearing at Barangay Cagay, Roxas City 3. Line clearing from Crossing Balijuagan to...
#TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura Accomplished: 1. Installation of 50 KVA temporary transformer at Barangay Aglalana, Dumarao 2. Replacement of 3 units of rotten poles (mano-mano) and rehabilitation of...
Proclamation No. 193 declares May as Electrical Safety Month in the Philippines, aiming to raise...
May 6, 2024, Monday The recent issuances of various regulatory agencies in the energy sector...
Accomplished: Replacement of ACSR #2 with insulated #1/0 from Solid to Unitop, Roxas Avenue, Roxas...
Employees of CAPELCO assigned at Burgos Sub-office and employees of Roxas City Area Office...
#TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura...