POST SCHEDULED POWER INTERRUPTION REPORT

POST SCHEDULED POWER INTERRUPTION REPORT

August 17, 2024, Saturday As scheduled: From 6:00 AM to 3:00 PM In actual: From 6:00 AM to 2:36 PM Areas affected: Barangays Dolores, Duran and Sta. Teresa, Dumalag and the whole of the Municipality of Tapaz Accomplished: Relocation of poles affected by DPWH road...

read more
SCHEDULED POWER INTERRUPTION

SCHEDULED POWER INTERRUPTION

Alas 8:00 sang aga tubtob Alas 5:00 sang hapon. Ang CAPELCO magapatigayon sang Line Clearing kag Maintenance. 1. AGOSTO 19, 2024 (Lunes nga adlaw) LUGAR NGA APEKTADO: -Sitio Insiwalan, Tapulang, Maayon. -Sitio Lagubang, Salgan, Maayon -Sitio Sulod, Piña, Maayon 1....

read more
EMERGENCY POWER INTERRUPTION

EMERGENCY POWER INTERRUPTION

August 15, 2024, Thursday, Around 5:40 PM Reason: Emergency Tripping of NGCP Panitan-Sapian transmission line Areas affected: Dao, Cuartero, Dumarao, Sigma, Mambusao, Sapian and Jamindan There are feeder lines that are not yet restored and we are working to restore...

read more
POST SCHEDULED POWER INTERRUPTION REPORT

POST SCHEDULED POWER INTERRUPTION REPORT

August 14, 2024, Wednesday As Scheduled: From 4:00 AM to 6:00 AM In actual: Feeder 2R – From 4:05 AM to 5:10 AM Feeder 4R – From 4:05 AM to 5:04 AM Reason: transfer of line connection of Barangay Tanza, Health Centrum at Barangay Banica and Barangay Bato to Feeder 2R....

read more

Other News

PUBLIC ADVISORY

To our valued Member-Consumer-Owners, please be informed that ALL AREA OFFICES and BAYAD CENTERS...