CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8

#TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog Accomplished: 1. Continued digging and installation of down guy wire for new line (relocation of 3-phase line) at Barangay San Esteban, Pilar 2. Installation of wire at...

read more
RECOGNITION OF AN HONEST SECURITY GUARD

RECOGNITION OF AN HONEST SECURITY GUARD

A special recognition was presented to SG Mark Clavero for his honesty while performing his job at CAPELCO. He found a wallet containing cash, IDs and other valuables whom he turned over to the management and was eventually returned to the owner. In recognition of his...

read more
FIRST FRIDAY MASS AND 7TH AGM MONTHLY MEETING

FIRST FRIDAY MASS AND 7TH AGM MONTHLY MEETING

Rev. Fr. Edcel Delfin who officiated the traditional First Friday Mass articulated the message of humility, mercy and forgiveness. He narrated the Gospels’ message of the story of Saint Matthew who rose up to became a saint from being a sinner, transformed into being...

read more
CONSOLIDATED TEAM ACCOMPLISHMENT BT9

CONSOLIDATED TEAM ACCOMPLISHMENT BT9

#TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura Accomplished: 1. Payout of (4/0) wire for the relocation of new 3-phase connection at Barangay San Esteban 2. Clearing of lines at Barangay Burias, Mambusao 3. Clearing of...

read more
POST SCHEDULED POWER INTERRUPTION REPORT

POST SCHEDULED POWER INTERRUPTION REPORT

As scheduled: From 8:30 AM to 5:00 PM In actual: From 8.30 AM to 3:45 PM Area Affected: Barangay Burias, Mambusao Accomplished: 1. Replacement of 3 units of rotten poles 2. Relocation of 2 units of poles 3. Replacement of polymer insulators 4. Line clearing operation...

read more