#TeamGeraldCondino BT 10 Team Members: G Condino, C Daliva, NM Distura, R Daliva and A Ordas Accomplished: June 2, 2024, Sunday 1. Replacement of rotten pole/ conversion of structure and rehabilitation of 15 kilowatt hour meters at Barangay Angub, Cuartero w/ BT 11...
POST SCHEDULED POWER INTERRUPTION REPORT AND PARALLEL ACTIVITIES
As scheduled: Morning From 5:00 AM to 7:00 AM Reason: NGCP temporary shut down of Panitan Substation due to Annual Preventive Maintenance Servicing Activities. In actual: From 5:00 to 6:40 AM 6:42 AM – Closed Feeders D1, D2, and D3 6:43 AM – Closed Feder D4 All...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT6
#TeamRonaldDili BT 6 Team Members: R Dili, R Delfin, JD Dice, R Degones and R Fuentes Accomplished: 1. Relocation of pole at Graceville, Barangay Tiza, Roxas City 2. Replacement of rotten pole at Sitio Marubrob, Barangay Parian, Sigma 3. Relocation of Pole at Barangay...
SCHEDULED POWER INTERRUPTION
Alas 8:00 sang aga tubtob Alas 4:30 sang hapon.Ang CAPELCO magapatigayon sang Line Clearing kag pag ilis sang Rotten Poles.LUGAR NGA APEKTADO:PRESIDENT ROXAS- BRGYS./STREETS OF: Marita, Mandulano, Quiajo, Pandan, Pinamihagan, Sangkal, Elizalde St., Redland kag...
SCHEDULED POWER INTERRUPTION
HUNYO 30, 2024 (Domingo nga adlaw) Alas 5:00 sang aga tubtob alas 7:00 sang aga Alas 4:00 sang hapon tubtob alas 6:00 sang hapon Ang NGCP temporaryo nga maga Shut Down sang Panitan Substation angot sa patigayunon nga Annual Preventive Maintenance Servicing Activities....
Other News
POST EMERGENCY POWER INTERRUPTION REPORT
July 5, 2024, Friday, From 1:11 PM to 1:37 PM Estimated Duration as Planned: 1 hour and 30 minutes...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 11
Working Crew: #TeamBobongSaron BT 11 Team Members: J Saron, R Fabella and M Deocampo Accomplished:...
POST EMERGENCY POWER INTERRUPTION REPORT
Due to bad weather condition and technical problem in the distribution lines causing line faults,...
SCHEDULED POWER INTERRUPTION
HULYO 5, 2024 (Biyernes nga adlaw)Alas 8:00 sang aga tubtob Alas 2:00 sang haponAng CAPELCO...
SCHEDULED POWER INTERRUPTION
HULYO 5, 2024 (Biyernes nga adlaw)Alas 8:30 sang aga tubtob Alas 5:00 sang haponAng CAPELCO...