WEEKLY TEAM ACCOMPLISHMENTS BT 8
#TeamGeraldCondino BT 8 Team Members: G Condino, C Daliva, NM Distura, M Umiten and A Ordas Accomplished: 1. Replacement of damaged 50 KVA transformer at Barangay Balijuagan, Roxas City 2. Replacement of damaged 50 KVA 2-phase connection, Dillera Rice Mill, Barangay...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 6
#TeamBobongSaron BT 6 Team Members: J Saron, F Fabella, M Batuampo, E Delos Santos and M. Deocampo Accomplished: Rephasing and clearing of lines at Sitio Baklayan, Sibaguan, Roxas City
CAPELCO SERVED AS RESOURCE PERSON IN THE SP COMMITTEE HEARING
Acting General Manager Engr. Edgar D. Diaz presented the perspective of an electric distribution utility during the Committee Hearing called by the Sangguniang Panlalawigan (SP) to elucidate on the widespread power interruption from January 2-5, 2024. The Committee...
CAPELCO 17TH TRI-MEDIA FELLOWSHIP 2024
Now on its 17th year, the annual tri-media initiatives of CAPELCO is an expression of its appreciation to the media entities and practitioners in Capiz for being in the forefront of delivering news and public information. This annual event is something that the media...
ECAR VI PARTICIPATED IN THE COORDINATION MEETING WITH NGCP
The electric cooperatives who are members of the Electric Cooperatives Association of Region VI (ECAR VI) participated in the coordination meeting with the National Grid Corporation of the Philippines (NGCP) Visayas System Operations, Visayas Operations and...
EMERGENCY POWER INTERRUPTION
Status: REPAIR ONGOING Wala sang kuryente sa karon ang Banwa sang Sapian kag pila ka kabarangayan sang Mambusao bangud sang aksidente nga nagluntad nga nag apekto sa banting sang 69 KV transmission line nga nahamtang sa Barangay Bula, Mambusao. Ang kuryente maibalik...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT9
#TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura Accomplished: 1. Relocation of 3-phase Line at Barangay Sta. Fe Water District at Barangay Sta. Fe, Pilar (with BT1_ 2. Pull out temporary 100kva transformer at Barangay...
ASSEMBLY MEETING AT SINONDOJAN BAPA
CAPELCO Representatives: A. Catalan, S Llorito and C Atando Purpose: Strengthening of the BAPA, capacitate BAPA leader and members, promote transparency and accountability and resolve organizational issues and concerns
CONSOLIDATED TEAM ACCOMPLISHMENTS BT2
#TeamKennyCordovero BT2 Team Members: K Cordovero, A Ferrer and R Distura Accomplished: Correction of grounding for Feeder 3 from Barangay Bailan, Pontevedra to Sitio Bantaaw, Cogon, Panitan
CONSOLIDATED TEAM ACCOMPLISHMENTS BT7
#TeamRamilDistura BT7 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog Accomplished: 1. Relocation of pole at Barangay Malag-it, Pontevedra 2. Installation of temporary 2 units of 50 KVA transformer at Maayon plaza for Maayon Municipal Fiesta 3....