SCHEDULED POWER INTERRUPTION
Alas 8:00 sang aga tubtob Alas 5:00 sang hapon.Ang CAPELCO magapatigayon sang Line Clearing kag Maintenance.1. HULYO 15, 2024 (Lunes nga adlaw)LUGAR NGA APEKTADO: Barangay Jaena Sur kag Agloloway, Jamindan.2. HULYO 16, 2024 (Martes nga adlaw)LUGAR NGA APEKTADO:...
EMERGENCY POWER INTERRUPTION
July 14, 2024, Sunday Emergency multiple tripping off of 15 MVA power transformer at Dao Substation. Affected areas are the municipalities of Dao, Cuartero, Dumarao, Dumalag, Tapaz and Sigma. Our engineers and maintenance crew are trying to restore power the soonest....
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 7
July 7-10, 2024, Sunday to Wednesday #TeamTamtamDangan BT7 Team Members: A Dangan, R Daliva, R Daliva, JP Hachuela and PP Fuentes with K Cordovero and R Distura, Jr. Accomplished: 1. Replacement of 2 units of rotten pole (mano-mano) and resagging of single phase line...
CONSOLIDATED TEAM ACCOMPLISHMENT BT9
July 9-16, 2024, Tuesday to Friday #TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura and with K Cordovero and R Distura, Jr. Accomplished: 1. Clearing of lines at Barangay Dolores, Dumalag 2. Replacement of damaged 37.5...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8
July 8-12, 2024, Monday to Friday #TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog with K Cordovero and R Distura, Jr. Accomplished: 1. Relocation of 2 units of 35 footer pole at Poblacion Dao Capiz. 2. Replacement of damaged...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 11
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 11 Working Crew: #TeamBobongSaron BT 11 Team Members: J Saron, R Fabella, M Batuampo, J Degones and M Deocampo Accomplished: 1. Replacement of pole at Barangay Cagay, Roxas City 2. Replacement of pole at Barangay Cudian, Ivisan 3....
CONSOLIDATED TEAM ACCOMPLISHMENTS ML2
#TeamLarryAcejo ML 2 Team Members: L Acejo, E Dublado, R Delfin, J Escalada and N Estorque Accomplished: 1. Line clearing at Barangay Mongpong to Barangay Gabuan, Roxas City 2. Line clearing at Barangay Dayao to Barangay Tanque, Roxas City 3. Line clearing at Barangay...
POST EMERGENCY POWER INTERRUPTION REPORT
July 10, 2024, Wednesday Due to bad weather condition and technical problem in the distribution lines causing line faults, a number of emergency power interruptions occurred in different areas in Capiz within the territorial responsibilities of various area offices....
SCHEDULED POWER INTERRUPTION
HULYO 12, 2024 (Biyernes nga adlaw)Alas 8:30 sang aga tubtob Alas 5:00 sang hapon.Ang CAPELCO magapatigayon sang Line Clearing kag Maintenance.LUGAR NGA APEKTADO: Barangay Sta. Fe, Casanayan, San Ramon, Balogo kag Dayhagan, Pilar.Gilayon man nga ibalik ang kuryente sa...
PARALLEL ACTIVITIES DURING THE SCHEDULED POWER INTERRUPTION
Accomplished: 1. Relocation of pole at Gabuan Roxas City 2. Replacement of Rotten Crossarm at Cals Lawaan Roxas City 3. Replacement of Damaged Pole at Banica Roxas City 4. Switching of breaker at Lawaan Substation 5. Replacement of Rotten Crossarm at Divine Jesus...