MEMBER-CONSUMER-OWNERS REQUEST ACTED
Accomplished: Re-tensioning of sagging secondary line Working Crew: #TeamPRAOBAPA, #TeamPRAOMaintenance and #TeamTSDComposite
POST EMERGENCY POWER INTERRUPTION REPORT MAMBUSAO AREA OFFICE
Reason: Tripping off of Feeder M2 (Municipality of Mambusao) due to toppled pine tree into the distribution line at Rizal Street, Poblacion, Mambusao
EMERGENCY REPAIR AND POWER RESTORATION
From 7:14 PM to 8:38 PM Areas affected: Feeder L1 Municipality of Pilar Working Crew: #TeamTSDComposite Team Members: RV Fadirugao, J Arroyo, A Daliva and F Distura #TeamPRAOMaintenance Team Members: B Arroyo, R Elebada and A...
PRE-EMPTIVE POWER INTERRUPTION
Time: Anytime soon Affected Areas: Municipality of Pilar Repair of three-phase line at San Fernando, Pilar affected by vehicular accident. Power will be restored once repair is completed. We are sorry for the...
SCHEDULED POWER INTERRUPTION
1. HUNYO 24, 2024 (Lunes nga adlaw)Alas 8:00 sang aga tubtob 5:00 sang haponAng CAPELCO magapatigayon sang Line Clearing & Maintenance.Apektado nga Lugar: Sitio Mambog kag portion sang Brgy. Agkilo , Panitan.-Sitio Gabuc kag portion sang Brgy. Conciencia,...
Happy General Managers’ Month!
In honor of General Managers Month, we recognize the invaluable leadership of our GMs and their dedication to fostering a positive and productive work environment.Happy General Managers’ Month! Thank you, AGM Edgar D....
POST EMERGENCY POWER INTERRUPTION REPORT
8:53 pm to 9:39 pmCause:Toppled tree causing trip-off of Feeder F4Areas affected: Ivisan, portion of Sigma and Timpas, Panitan.CHRONOLOGY8:53 pm - Trip-off Feeder F49:02 pm - Restored Feeder F4 except Basiao, Ivisan9:39 pm - Feeder F4 totally...
POST EMERGENCY POWER INTERRUPTION REPORT
7:20 pm to 8:35 pm Cause: Disconnected three-phase line at Barangay Palaguian Maayon causing the tripping off of Feeder 3. Areas affected: Maayon, portion of Panitan and portion of Dao.
MEMBER-CONSUMER-OWNERS REQUEST ACTED
• Replacement of Pole at Barangay Tanza Sur, Panay • Relocation of pole at Poblacion Ilaya, Panay Working Crew: #TeamBobongSaron BT 11 Team Members: J Saron, R Fabella, J Degones, J Hachuela and M Deocampo
POST SCHEDULED POWER INTERRUPTION REPORT
From 8:00 AM to 4:30 PM Areas affected: Barangays Concepcion, San Roque, San Agustin, San Martin and portion of Sta. Teresa, Dumalag Accomplished: Relocation, conversion and clearing of lines Working Crews: #TeamTamtamDangan BT7 Team Members: A Dangan, R Daliva, J...