ANG MALAIN NGA PANAHON ANG GINTUNAAN SANG MALAPNAGON NGA BROWNOUT
Suno sa impormasyon nga ginpaabot sang mga Area Offices sa Segundo Distrito, masyado kabaskog sang hangin nga may dala nga ulan ang nangin rason sa likod sang malapnagon nga emergency power interruption. Indi nga mga hitabo wala sa aton ang kontrol kag ang sarang na...

PARALLEL ACTIVITIES WHILE THE 15 MVA IS BEING PREPARED FOR ENERGIZATION AT DAO SUBSTATION
CAPELCO CONSTRUCTION CREWS Accomplished: 1. Relocation of 2 poles and rehabilitation of kilowatt hour meters at Sitio Ayuyan, Barangay Sto. Angel, Dumalag 2. Replacement of rotten pole at Barangay Angub, Cuartero (Double circuit) and rehabilitation of kilowatt hour...

SCHEDULED POWER INTERRUPTION
HUNYO 5, 2024 (Miyerkules nga adlaw)5:00 tubtob 6:30 sang agaAng CAPELCO magapatigayon sang pag Reconfigure sang Feeder 7R sa Lawaan Substation.Lugar nga Apektado:FEEDER 7R - Pueblo De Panay, kaupod ang Robibnsons kag Roxas City PNP.FEEDER 8R - Brgy. Lawaan, Arcabalo...

MEMBER-CONSUMER-OWNER REQUEST ACTED
Sitio Utod, Barangay San Miguel, Dumalag Relocation of three-phase line Working Crew: #TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R...

SCHEDULED POWER INTERRUPTION
HUNYO 9, 2024 (Domingo nga adlaw) 5:00 sang aga tubtob 2:00 sang hapon Ang CAPELCO magapatigayon sang Preventive Maintenance Servicing o PMS sang Burgos Substation. Lugar nga Apektado: FEEDER B1 - Crossing Petron to City Mall Arnaldo Boulevard, Burgos, Legaspi,...

CONSOLIDATED TEAM ACCOMPLISHMENTS BT6
#TeamRonaldDili BT 6 Team Members: R Dili, R Delfin, JD Dice and R Fuentes Accomplished: 1. Relocation of pole at Barangay Culajao Roxas City 2. Installation of intermediate pole at Barangay Ilamnay, Panay (FB Complaint) 3. Relocation of pole at Barangay Cagay, Roxas...

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 11
#TeamBobongSaron BT 11 Team Members: J Saron, R Fabella, JD Batuampo and M Deocampo Accomplished: 1. Assisted in the Roxas City scheduled power interruption at Barangay Adlawan and in Panay Area 2. Assisted in the Power interruption in the Second District by...

PARALLEL ACTIVITIES WHILE THE 15 MVA IS BEING PREPARED FOR ENERGIZATION AT DAO SUBSTATION
DAO AREA OFFICE Accomplished: • Replacement of polymer to porcelain and replacement of damaged insulator at from Barangay Nagba to Barangay Agcabugao, Cuartero line section and from Barangay Codingle to Barangay Dacuton, Dumarao line section Working Crew:...

TWO WEEKS OF CONSOLIDATED TEAM ACCOMPLISHMENTS BT10
#TeamGeraldCondino BT 10 Team Members: G Condino, C Daliva, NM Distura, R Daliva and A Ordas Accomplished: 1. Assisted in the scheduled power interruption at Roxas City area to include works to replace rotten Cross arm at San Antonio Village, Baybay, Roxas City from...

POST EMERGENCY POWER INTERRUPTION REPORT
Reason: Burned grounding cable at Lawaan Substation, Lawaan, Roxas City Chronology of Time and Areas Affected: 6:54 PM to 6:55 PM - Tripping off of feeder 1R, 2R, 3R, 5R, 7R and 8R (Areas affected: Feeder 1R – Roxas Avenue, Punta Tabuc, Cagay, Sibaguan, Balijuagan,...