CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8
#TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog Accomplished: Relocation of 2 units 30 foot pole and transfer of metering at Poblacion Tabuc,...

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 9
#TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura Accomplished: 1. Pull out 50kva rental transformers at Barangay Sta. Cruz, Dumalag 2. Pull out 50kva rental transformers at Barangay Bag-ong Barrio, Tapaz 3. Pull out...

CAPELCO VISITED BY STUDENTS FROM CPC ENGINEERING
A group for electrical and computer engineering students of Colegio dela Purisima Concepcion visited CAPELCO to conduct actual observation on its operation and to learn how an electric distribution utility operates. They appreciated having observed the actual...

PAGTAAS SANG KONSUMO KAG PAGTAAS SANG PRESYO SANG KURYENTE MAGA RESULTA SA MATAAS NGA BALAYARAN
Ang pagtaas sang aton konsumo kag ang pagmahal sang presyo sang kuryente sa mekado indi maayo kumbinasyon. Ang resulta sini amo ang mataas nga balayaran sa kuryente nga masami sentro sang reklamo sang mga konsumidor. Sa pagtuon nga ginhiwat sang mga engineers sang...

ROXAS CITY AREA OFFICE CLOSED

POST EMERGENCY POWER INTERRUPTION REPORT
Areas Affected:Reason: Tripping off of NGCP Panitan-Sapian Transmission Line due to unknown faultAreas Affected:Mambusao Substation: Municipalities of Sapian, Mambusao and JamindanDao Substation: Municipalities of Dao, Cuartero, Dumarao, Dumalag and...

MEMBER-CONSUMER-OWNER REQUEST ACTED
Bangga-an, PanitanAccomplished: Replacement of rotten poleWorking Crew: #TeamTamtamDanganBT7 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes

JOINT TEAM ACCOMPLISHMENTS BT 6 AND ISUZU 2
#TeamBobongSaron BT 11 Team Members: J Saron, R Fabella, JD Batuampo and M Deocampo Accomplished: 1. Pull out of transformer at Adlawan, Roxas City 2. Hole digging at Sitio Lebanon, Bonga, Panay 3. Continued rehabilitation of lines and Kilowatt hour meters at Sitio...

RESPONSE TO 48TH AGMA PRIORITIES
Accomplished: Rephasing of lines from secondary line to single phase and installation of additional 25 KVA transformer due to low voltage at Barangay Quios, Panitan Working crew: #TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R...

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 7
#TeamTamtamDangan BT7 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes Accomplished: 1. Rephasing of lines from secondary line to single phase (4 Span) and installation of additional 25 KVA transformer at BAPA 3, Barangay Enseñagan, Panitan to...