POST EMERGENCY POWER INTERRUPTION REPORT

POST EMERGENCY POWER INTERRUPTION REPORT

Affected Areas: Feeder 2R – Milibili, Malipayon Village and Tiza Accomplished: Replaced toppled pole along Datiles Street, Tiza, Roxas City Working Crew: #TeamGeraldCondino BT 10 Team Members: G Condino, C Daliva, NM Distura, M Umiten and A Ordas #TeamRCAOMaintenance...

CONSOLIDATED TEAM ACCOMPLISHMENT BT11

CONSOLIDATED TEAM ACCOMPLISHMENT BT11

#TeamBobongSaron BT 11 Team Members: J Saron, R Fabella, M Batuampo and M Deocampo Accomplished: 1. Correction of low elevation wire, duplex and telecom wires from Barangay Cagay to Barangay Dayao 2. Installation of intermediate pole 3. Extension of line and...

MEMBER-CONSUMER-OWNER REQUEST ACTED

MEMBER-CONSUMER-OWNER REQUEST ACTED

Sitio Ilaya, Barangay Dinginan, Roxas CityAccomplished: Extension of line and rehabilitation of kilowatt hour metersWorking Crew:#TeamBobongSaronBT 11 Team Members: J Saron, R Fabella, M Batuampo, E Delos Santos and M Deocampo

POST EMERGENCY POWER INTERRUPTION REPORT

POST EMERGENCY POWER INTERRUPTION REPORT

Areas affected: Barangay Manapao, Gabuc and Cabugao, Pontevedra Cause: Toppled wooden electrical pole caught by grassfire at Barangay Gabuc, Pontevedra Responding crew: #TeamPRAOMaintenance and BAPA Crew Team Leader: B Dellota Team members: J Paderes and N Tumlos With...

SCHEDULED POWER INTERRUPTION

SCHEDULED POWER INTERRUPTION

8:30 sang aga tubtob 5:00 sang haponAng CAPELCO magapatigayon sang Line Maintenance kag Clearing.1. ABRIL 29, 2024 (Lunes nga adlaw)LUGAR NGA APEKTADO:-Brgy. Solo, Linampongan kag sitio Mantawad, Malag-it, Pontevedra.2. ABRIL 30, 2024 (Martes nga adlaw)LUGAR NGA...

POST SCHEDULED POWER INTERRUPTION REPORT

POST SCHEDULED POWER INTERRUPTION REPORT

From 8:30 AM to 5:00 PM Areas affected: Barangay Matagnop, Malonoy, Agtanguay, Daplas, Ilas Sur, Ilas Norte aand Centro, Dao. Accomplished: Line clearing operation Working Crew: #NLBEnterprises – Line clearing contractor

EMERGENCY REPLACEMENT AND REPAIR

EMERGENCY REPLACEMENT AND REPAIR

New Road, Barangay Banica, Roxas City Work Done: Installation of Blade Disconnect Switch in order to address recurring and multiple line trippings of 4R Feederline #TeamGeraldCondino BT 10 Team Members: G Condino, C Daliva, NM Distura, M Umiten and A...

POST EMERGENCY POWER INTERRUPTION REPORT

POST EMERGENCY POWER INTERRUPTION REPORT

 Barangay Monteflor, Pilar Power out: 1:00 AM Power restored: 9:30 AM Cause: Disconnected 3-span of single-phase line hit by toppled Mahogany tree Responding Crew: #TeamPRAOMaintenance and BAPA Crew Team Leader: B Dellota Team Members: J Paderes, N Tumlos, J Dorado...

CONSOLIDATED TEAM ACCOMPLISHMENTS ML2

CONSOLIDATED TEAM ACCOMPLISHMENTS ML2

#TeamArlanDangan ML 2 Team Members: A Dangan, E Dublado, R Delfin, J Escalada, N Estorque and L Acejo Accomplished: 1. Line clearing at Sitio Ilaya, Barangay Lanot, Roxas City 2. Line clearing at Barangay Cagay, Roxas City 3. Line clearing from Crossing Balijuagan to...

CONSOLIDATED TEAM ACCOMPLISHMENT BT9

CONSOLIDATED TEAM ACCOMPLISHMENT BT9

#TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura Accomplished: 1. Installation of 50 KVA temporary transformer at Barangay Aglalana, Dumarao 2. Replacement of 3 units of rotten poles (mano-mano) and rehabilitation of...