POST EMERGENCY POWER INTERRUPTION REPORT

POST EMERGENCY POWER INTERRUPTION REPORT

Areas affected: Barangay Bonga to Barangay Pawa, Panay line section including coastal barangays of Panay Reason: Grounded cross arm and burned wooden pole due to Intrusion of lizard Responding Crew: #TeamGeraldCondino BT 8 Team Members: G Condino, C Daliva, NM...

WEEKLY AND CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8

WEEKLY AND CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8

#TeamGeraldCondino BT 8 Team Members: G Condino, C Daliva, NM Distura, M Umiten and A Ordas Accomplished: 1. Complete grounding installation for 3-phase line at Pueblo de Panay, Lawaan to Dinginan, Roxas City 2. Pull-out of old pole and transfer of line to new erected...

SCHEDULED POWER INTERRUPTION

SCHEDULED POWER INTERRUPTION

8:30 sang aga tubtob 4:30 sang haponAng CAPELCO mapatigayon sang Line Maintenance kag Clearing.1. MARSO 11, 2024 (Lunes nga adlaw)LUGAR NGA APEKTADO:-Brgy. Pasugue kag Cala-an Sur, Panitan-Brgy. Lacaron, Dao2. MARSO 12, 2024 (Martes nga adlaw)LUGAR NGA APEKTADO:-Brgy....

CONSOLIDATED TEAM ACCOMPLISHMENTS BT7

CONSOLIDATED TEAM ACCOMPLISHMENTS BT7

The crew are staying at Tapaz to maximize their accomplishments #TeamRamilDistura BT7 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog Accomplished: 1. Replacement of 3 units of capacitor at Barangay San Jose, Tapaz 2. Digging and erection of 5...

JOINT TEAM ACCOMPLISHMENTS BT1, BT2 AND BT7

JOINT TEAM ACCOMPLISHMENTS BT1, BT2 AND BT7

Accomplished: Pull out of idle materials, transfer/rehabilitation of kilowatt hour meters and upgrading of transformer from 25 KVA to 37.5 KVA at Barangay Dangula, Dumarao Working crews: #TeamTamtamDangan BT1 Team Members: A Dangan, R Daliva, J Penuela, J Degones and...

CONSOLIDATED TEAM ACCOMPLISHMENTS BT1

CONSOLIDATED TEAM ACCOMPLISHMENTS BT1

#TeamTamtamDangan BT1 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes Accomplished: 1. Installation of 2-span secondary line for health center and evacuation center at Barangay Tabun- acan. Pilar 2. Replacement of rotten pole, relocation of pole...

CONSOLIDATED TEAM ACCOMPLISHMENTS BT9

CONSOLIDATED TEAM ACCOMPLISHMENTS BT9

#TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura Accomplished: 1. Installation of 4-span secondary line and transfer/rehabilitation of kilowatt hour meters at Barangay Monteflor,Pilar 2. Insertion of intermediate pole...

AGM MONTHLY MEETING NUMBER 3

AGM MONTHLY MEETING NUMBER 3

CAPELCO Burgos Street Office The monthly meeting with Acting General Manager Engr. Edgar D. Diaz was held earlier today of which employees that are based in Roxas City were treated to a presentation of the previous month’s accomplishments and the current month’s...