POST EMERGENCY POWER INTERRUPTION REPORT
June 7, 2024, from 6:47 PM to 7:05 PM and from 7:33 PM to 7:40 PM The 20 MVA Power transformer at Lawaan Substation experienced multiple tripping at the height of lightning strike and thunderstorm, as follows: • From 6:47 PM to 7:05 PM • From 7:33 PM to 7:40 PM...
BILLING RATE FOR JUNE 2024

SCHEDULED POWER INTERRUPTION
HUNYO 8, 2024 (Sabado nga adlaw)10:00 tubtob 11:00 sang agaAng CAPELCO maga conduct sang timing test sang bag o nga 15MVA sa Dao SubstationLUGAR NGA APEKTADO: Municipalities of Dao, Cuartero, Dumarao, Dumalag, Tapaz kag Sigma.Gilayon man nga ibalik ang kuryente sa...