POST SCHEDULED POWER INTERRUPTION REPORT
July 5, 2024, Friday As scheduled: From 8:30 AM to 5:00 PM In actual: From 8.30 AM to 3:45 PM Area Affected: Barangay Burias, Mambusao Accomplished: 1. Replacement of 3 units of rotten poles 2. Relocation of 2 units of poles 3. Replacement of polymer insulators 4....
SCHEDULED POWER INTERRUPTION
HULYO 9, 2024 (Martes nga adlaw) Alas 4:00 tubtob Alas 8:00 sang aga Ang National Grid Corporation of the Philippines o NGCP TEMPORARYO nga maga shut-down sang CAPELCO Feeders (69KV Panitan-Roxas Transmission Line kag Timpas Power Transformer 1) para mag patigayon...
SCHEDULED POWER INTERRUPTION
Alas 8:00 sang aga tubtob Alas 5:00 sang haponAng CAPELCO mapatigayon sang Line Clearing kag Maintenance1. HULYO 8, 2024 (Lunes ng adlaw)LUGAR NGA APEKTADO: Sitio Bughaan kag sitio Hacienda Tunga, Dulangan, Pilar2. HULYO 9, 2024 (Martes nga adlaw)LUGAR NGA APEKTADO:...