PARALLEL ACTIVITIES DURING THE SCHEDULED POWER INTERRUPTION
May 18, 2024, Saturday Taking time that power is out due to the Preventive Maintenance Servicing of President Roxas Substation, CAPELCO’s construction crew and the maintenance crew of President Roxas Area Office conducted parallel activities to make use of the time...
POST SCHEDULED POWER INTERRUPTION REPORT
May 18, 2024, Saturday As scheduled: From 5:30 AM to 1:30 PM In actual: From 5:30 AM to 12:26 PM Areas affected: All Feeders connected to President Roxas Substation Feeder L1- Municipality of Pilar Feeder L2 – Municipality of President Roxas Feeder L3 – Island...