CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8
July 29 to August 2, 2024, Monday to Friday #TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog Accomplished: 1. Replacement of rotten pole at Barangay Poblacion Sur, Sigma 2. Replacement of rotten pole at Barangay Bita, Dao 3....
MONTH LONG CONSOLIDATED TEAM ACCOMPLISHMENTS BT10
July 1 – 30, 2024, Whole month of July 2024 #TeamGeraldCondino BT 10 Team Members: G Condino, C Daliva, NM Distura, M Umiten and A Ordas Accomplished: 1. Replacement of damage 50 KVA transformer at Sitio Tagudtod, Poblacion, Ivisan 2. Installation of groundings...
POST SCHEDULED POWER INTERRUPTION REPORT