July 6, 2024, Saturday Tinaytayan, Dumarao Accomplished: Replacement of rotten pole July 6, 2024, Saturday Calanza Street, Poblacion Tacas, Cuartero Accomplished: Relocation of pole Working Crew: #TeamTamtamDangan BT7 Team Members: A Dangan, R Daliva, R Daliva, JP...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8
July 1-5, 2024, Monday to Friday #TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog Accomplished: 1. Continued digging and installation of down guy wire for new line (relocation of 3-phase line) at Barangay San Esteban, Pilar...
CONSOLIDATED TEAM ACCOMPLISHMENT BT9
July 2-6, 2024, Tuesday to Saturday #TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura Accomplished: 1. Payout of (4/0) wire for the relocation of new 3-phase connection at Barangay San Esteban 2. Clearing of lines at...
POST SCHEDULED POWER INTERRUPTION REPORT
July 5, 2024, Friday As scheduled: From 8:30 AM to 5:00 PM In actual: From 8.30 AM to 3:45 PM Area Affected: Barangay Burias, Mambusao Accomplished: 1. Replacement of 3 units of rotten poles 2. Relocation of 2 units of poles 3. Replacement of polymer insulators 4....