CONSOLIDATED TEAM ACCOMPLISHMENTS ML2
May 11-13, 2024, Saturday to Monday #TeamArlanDangan ML 2 Team Members: A Dangan, E Dublado, R Delfin, J Escalada, N Estorque and L Acejo Accomplished: 1. Line clearing at Dao Area 2. Line clearing at Mambusao Area 3.Line clearing from Sitio San Vicente Barangay Bato...
POST SCHEDULED POWER INTERRUPTION REPORT
May 12, 2024, Sunday As scheduled: From 5:30 AM to 1:30 PM In Actual: From 5:32 AM to 11:01 AM Accomplished; Conduct of Preventive Maintenance Servicing of Dao Substation Areas affected: Municipalities of Dao, Cuartero, Dumarao, Dumalag and...
PARALLEL ACTIVITIES DURING THE SCHEDULED POWER INTERRUPTION
May 12, 2024, Sunday Taking time that power is out due to the Preventive Maintenance Servicing of Dao Substation, CAPELCO’s construction crew and the maintenance crew of Dao Area Office conducted parallel activities to make use of the time that power is out....
POST EMERGENCY POWER INTERRUPTION REPORT
May 12, 2024, Sunday From 4:11 AM to 8:58 AM Affected areas: Municipality of Sapian, Mambusao and Jamindan Chronology: • 4:11AM – Tripping off of 69 KV tapping point at Bangkal, Maninang affecting Sapian, Mambusao and Jamindan • 4:53 AM – Normalized all feeder lines •...