July 1-3 and July 6, 2024, Monday to Wednesday and Saturday #TeamTamtamDangan BT7 Team Members: A Dangan, R Daliva, R Daliva, JP Hachuela and PP Fuentes Accomplished: 1. Replacement of 2 units of rotten poles (mano-mano) at Sitio Mangga, Barangay Atiplo, Mambusao 2....
POST SCHEDULED POWER INTERRUPTION REPORT

POST SCHEDULED POWER INTERRUPTION REPORT

July 5, 2024, Friday As scheduled: From 8:30 AM to 5:00 PM In actual: From 8.30 AM to 3:45 PM Area Affected: Barangay Burias, Mambusao Accomplished: 1. Replacement of 3 units of rotten poles 2. Relocation of 2 units of poles 3. Replacement of polymer insulators 4....
POST EMERGENCY POWER INTERRUPTION REPORT

POST EMERGENCY POWER INTERRUPTION REPORT

July 5, 2024, Friday, From 1:11 PM to 1:37 PM Estimated Duration as Planned: 1 hour and 30 minutes Actual Duration: 26 Minutes only Areas Affected: Feeder 3 – Portion of Maayon and Panitan Accomplished : Replaced broken pin and suspension insulators at Cadio Crossing...