CONSOLIDATED TEAM ACCOMPLISHMENTS BT 7
#TeamTamtamDangan BT7 Team Members: A Dangan, R Daliva, R Daliva, JP Hachuela and PP Fuentes Accomplished: 1. Replacement of 2 units of rotten poles (mano-mano) at Sitio Mangga, Barangay Atiplo, Mambusao 2. Payout of (4/0) wire for the relocation of new 3-phase...
POST SCHEDULED POWER INTERRUPTION REPORT
As scheduled: From 8:30 AM to 5:00 PM In actual: From 8.30 AM to 3:45 PM Area Affected: Barangay Burias, Mambusao Accomplished: 1. Replacement of 3 units of rotten poles 2. Relocation of 2 units of poles 3. Replacement of polymer insulators 4. Line clearing operation...
SCHEDULED POWER INTERRUPTION
HULYO 9, 2024 (Martes nga adlaw) Alas 4:00 tubtob Alas 8:00 sang aga Ang National Grid Corporation of the Philippines o NGCP TEMPORARYO nga maga shut-down sang CAPELCO Feeders (69KV Panitan-Roxas Transmission Line kag Timpas Power Transformer 1) para mag patigayon...
SCHEDULED POWER INTERRUPTION
Alas 8:00 sang aga tubtob Alas 5:00 sang haponAng CAPELCO mapatigayon sang Line Clearing kag Maintenance1. HULYO 8, 2024 (Lunes ng adlaw)LUGAR NGA APEKTADO: Sitio Bughaan kag sitio Hacienda Tunga, Dulangan, Pilar2. HULYO 9, 2024 (Martes nga adlaw)LUGAR NGA APEKTADO:...
POST EMERGENCY POWER INTERRUPTION REPORT
July 5, 2024, Friday, From 1:11 PM to 1:37 PM Estimated Duration as Planned: 1 hour and 30 minutes Actual Duration: 26 Minutes only Areas Affected: Feeder 3 – Portion of Maayon and Panitan Accomplished : Replaced broken pin and suspension insulators at Cadio Crossing...
Other News
SCHEDULED EMERGENCY POWER INTERRUPTION
July 21, 2024, Sunday, As scheduled: From 4:00 AM to 5:00 AM In actual; From 4:06 AM to 4:33 AM...
CONTINUED HOUSEWIRING OF SEMA BENEFICIARIES
July 18, 2024, Bilao, Sapian The installation of housewiring to qualified beneficiaries of the...
SCHEDULED POWER INTERRUPTION
JULY 20, 2024 (Sabado nga adlaw)1. Ang CAPELCO magapatigayon sang pag saylo sang mga poste.Alas...
POST EMERGENCY POWER INTERRUPTION REPORT
July 18, 2024, Thursday, From 8:34 AM to 8:48 AM Areas affected: Feeder 1 – Municipality of Panay,...
MEMBER-CONSUMER-OWNER’S REQUEST ACTED
July 16, 2024, Tuesday LINE CLEARING Dumpsite, Sibaguan Ilaya, Roxas City Working Crew:...