SCHEDULED POWER INTERRUPTION
Alas 8:30 sang aga tubtob alas 5:00 sang hapon.Ang CAPELCO magapatigayon sang line clearing.1. Nobyembre 4, 2024 (Lunes nga adlaw)Lugar nga Apektado: Brgy. Sto. Rosario kag Sta. Monica, Dumalag2. Nobyembre 5, 2024 (Martes nga adlaw)Lugar nga Apektado: Brgy. Najus-an,...
SCHEDULED POWER INTERRUPTION
Nobyembre 3, 2024 (Domingo nga adlaw)Alas 8:00 sang aga tubtob alas 12:00 sang udto.Ang CAPELCO magapatigayon sang clearing of lines kag correction of lines.Lugar nga Apektado: Brgy. Dumolog (porsyon), Cogon kag Punta Cogon, Roxas City.Gilayon man nga ibalik ang...
MEMBER-CONSUMER-OWNER’S REQUEST ACTED
October 29, 2024 (Tuesday) Sitio Rizal, Barangay Pinamalatican, Sigma. Working Team: #TeamMakiBitoon ML-1 Team Members: M. Bitoon, R. Durias, J. Bereber, E. Bithao Accomplished: Line...
CONSOLIDATED TEAM ACCOMPLISHMENTS ML2
October 21-25, 27 and 28, 2024 #TeamLarryAcejo ML 2 Team Members: L Acejo, E Dublado, R Delfin, J Escalada and N Estorque Accomplished: 1. Line clearing at Barangay Basiao, Ivisan and Westlake Subdivision, Dayao, Roxas City 2. Line clearing at Barangay Punta Cogon 3....
SCHEDULED POWER INTERRUPTION
Oktubre 30, 2024 (Miyerkules nga adlaw)Alas 8:00 sang aga tubtob alas 4:00 sang hapon.Ang CAPELCO magapatigayon sang Line Clearing.Lugar nga Apektado: Hortus Botanicus, PHILVOLCS kag SWARA SUG Media sa Brgy. Milibili, Roxas City.Gilayon man nga ibalik ang kuryente sa...
SCHEDULED POWER INTERRUPTION
Oktubre 30, 2024 (Miyerkules nga adlaw)Alas 6:00 sang aga tubtob alas 3:00 sang hapon.Ang CAPELCO magapatigayon sang pag saylo sang poste angot sa DPWH Road Widening Project kag Line Clearing.Lugar nga Apektado:Roxas City - porsyon sang Brgy. Adlawan, Loctugan kag...
POST SCHEDULED POWER INTERRUPTION REPORT
October 27, 2024, Sunday As scheduled: From 7:00AM to 3:00 PM In actual: From 7:06 AM to 2:50 PM Areas affected: Arnaldo Blvd. (Portion), Baybay and Culasi, Roxas City. Accomplished: Line clearing operation and replacement of rotten poles. Working crews:...
SCHEDULED POWER INTERRUPTION
Oktubre 29, 2024 (Martes nga adlaw)Alas 8:30 sang aga tubtob alas 5:00 sang hapon.Ang CAPELCO magapatigayon sang Line Clearing.Lugar nga Apektado: Brgy. Bilao tubtob Lonoy, Sapian Line Section.Gilayon man nga ibalik ang kuryente sa ti-on nga matapos ang...
EMERGENCY POWER INTERRUPTION
October 25, 2024, Friday around 8:30 am Emergency Line Clearing due to toppled bamboo trees in the 3 Phase Line. Status: Ongoing Affected Areas: Brgy. Basiao, Balaring, Matnog, Agmalobo and Agustin Navarra,...
POST SCHEDULED POWER INTERRUPTION REPORT
October 24, 2024, Thursday As scheduled: From 8:30 AM to 5:00 PM In actual: From 8:30 AM to 4:30 PM Areas affected: 7-11 Jamindan, Jamindan Water System, Barangays Agambulong, San Vicente, Pangabat and Masgrau, Jamindan. Accomplished: Line clearing operation,...