SCHEDULED POWER INTERRUPTION
Alas 8:00 sang aga tubtob Alas 5:00 sang hapon.Ang CAPELCO magapatigayon sang Line Clearing kag Maintenance.1. HULYO 18, 2024 (Huwebes nga adlaw)LUGAR NGA APEKTADO: Barangay Salgan, Piña kag Tapulang, Maayon.2. HULYO 19, 2024 (Biyernes nga adlaw)LUGAR NGA APEKTADO:...

CONSOLIDATED TEAM ACCOMPLISHMENTS BT6
July 10-14, 2024, Wednesday to Sunday #TeamRonaldDili BT 6 Team Members: R Dili, R Delfin, JD Dice and R Fuentes Accomplished: 1. Replacement of rotten pole at Barangay Cagay, Roxas City 2. Replacement of rotten pole at Sitio Manaulan, Barangay Cudian, Ivisan 3....

POST EMERGENCY POWER INTERRUPTION REPORT
July 11-14, 2024, Thursday to Sunday Due to bad weather condition and technical problem in the distribution lines causing line faults, a number of emergency power interruptions occurred in different areas in Capiz within the territorial responsibilities of various...

CAPELCO OFFICERS PARTICIPATED IN LEADERSHIP WORKSHOP
“Be part of the solution, not part of the problem.” This is the central message of Acting General Manager (AGM) Engr. Edgar D. Diaz during the one-day Enhancing Personal and Professional Development Workshop for CAPELCO selected officers conducted as part of...

HOUSEWIRING INSTALLATION FOR SEMA BENEFICIARIES
It took long hours of walk before engineering students who are undergoing on-the-job training (OJT) at CAPELCO reached the residences of beneficiaries of Socialized Energization of Marginalized Applicants (SEMA) for electric service connections at Barangay...

SCHEDULED POWER INTERRUPTION
Alas 8:00 sang aga tubtob Alas 5:00 sang hapon.Ang CAPELCO magapatigayon sang Line Clearing kag Maintenance.1. HULYO 15, 2024 (Lunes nga adlaw)LUGAR NGA APEKTADO: Barangay Jaena Sur kag Agloloway, Jamindan.2. HULYO 16, 2024 (Martes nga adlaw)LUGAR NGA APEKTADO:...

EMERGENCY POWER INTERRUPTION
July 14, 2024, Sunday Emergency multiple tripping off of 15 MVA power transformer at Dao Substation. Affected areas are the municipalities of Dao, Cuartero, Dumarao, Dumalag, Tapaz and Sigma. Our engineers and maintenance crew are trying to restore power the soonest....

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 7
July 7-10, 2024, Sunday to Wednesday #TeamTamtamDangan BT7 Team Members: A Dangan, R Daliva, R Daliva, JP Hachuela and PP Fuentes with K Cordovero and R Distura, Jr. Accomplished: 1. Replacement of 2 units of rotten pole (mano-mano) and resagging of single phase line...

CONSOLIDATED TEAM ACCOMPLISHMENT BT9
July 9-16, 2024, Tuesday to Friday #TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura and with K Cordovero and R Distura, Jr. Accomplished: 1. Clearing of lines at Barangay Dolores, Dumalag 2. Replacement of damaged 37.5...

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8
July 8-12, 2024, Monday to Friday #TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog with K Cordovero and R Distura, Jr. Accomplished: 1. Relocation of 2 units of 35 footer pole at Poblacion Dao Capiz. 2. Replacement of damaged...