POST SCHEDULED POWER INTERRUPTION REPORT
From 6:00 AM to 3:00 PM Areas affected: • Barangay Cabugcabug, Badiangon, Bayuyan, Sto. Niño, Carmencita, Goce and Manoling, President Roxas. • Barangay Yating, San Silvestre and Tabun-acan, Pilar. Accomplished: Conversion of line from V-phase to 3-phase and line...

CONSOLIDATED TEAM ACCOMPLISHMENT BT11
#TeamBobongSaron BT 11 Team Members: J Saron, R Fabella, M Batuampo and M Deocampo Accomplished: 1. Relocation of pole at Barangay Mianay, Ivisan 2. Correction of service drop wires and telcos wire at Barangay Dayao, Roxas...

WEEKLY AND CONSOLIDATED TEAM ACCOMPLISHMENTS BT 10
#TeamGeraldCondino BT 10 Team Members: G Condino, C Daliva, NM Distura, M Umiten and A Ordas Accomplished: 1. Assisted during the power interruption from Bonga, Mambusao to Linambasan, Jamindan o Relocation/conversion of pole from C-4 to C-15 o Replacement of polymer...

SCHEDULED POWER INTERRUPTION
1. ABRIL 25, 2024 (Huwebes nga adlaw) 8:30 sang aga tubtob 5:00 sang hapon Ang CAPELCO magapatigayon sang Line Maintenance kag Clearing. LUGAR NGA APEKTADO: -Brgy. Matagnop, Malonoy, Agtanguay, Daplas, Ilas Sur, Ilas Norte kag Centro, Dao. 2. ABRIL 26, 2024 (Biyernes...

AREA OFFICE MAINTENANCE ACTIVITY
Dumalag Area Office Various Dates Accomplished: Rehabilitation of metering in the following barangays • Lagdungan, Tapaz • Duran, Dumalag • San Roque Proper, San Roque 1, Dumalag • Poblacion Ilawod, Dumalag Working Crew: #TeamDUMAOMaintenance Team Members: M Antonio,...

AREA OFFICE MAINTENANCE ACTIVITY
President Roxas Area Office Accomplished: Insertion of pole at Sitio Tinondojan, Barangay Poblacion, President Roxas Working Crew: #TeamPRAOMaintenance Team Leader: B Dellota Team Members: J Paderes, N Tumlos, R Elebada and J Quiachon With On-The-Job trainees (OJT)...

BARANGAY POWER ASSOCIATION (BAPA) STRENGTHENING ACTIVITIES
Mambusao Area Office Parian BAPA 2, Parian, Sigma Coordination meeting facilitated by MAO personnel A Catalan and R Velarde

CONSOLIDATED TEAM ACCOMPLISHMENT BT11
#TeamBobongSaron BT 11 Team Members: J Saron, R Fabella, M Batuampo and M Deocampo Accomplished: 1. Pull out of 25 KVA temporary transformer at Barangay Ilaya-Ivisan

AREA OFFICE MAINTENANCE ACTIVITY
Dumalag Area Office Accomplished: Transfer of line and kilowatt hour meters to new pole at Poblacion Ilaya, Dumalag. Working Crew: #TeamDUMAOMaintenance Team Members: M Antonio, J Fedalgo, P Sy, N Facinal and R. Delfin Works requested by Punong Barangay Hon. Arnolfo...

THIRD MONTHLY MEETING FOR 2024 OF MANAGERS, SUPERVISORS AND SECTION HEADS WITH ACTING GENERAL MANAGER
The meeting was to review key things that has to be done and to address the recurring concerns involving inter-office collaboration with foremost question from Acting General Manager (AGM) Engr. Edgar D. Diaz – What has been done and what needs to be done? The...