CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8
#TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog Accomplished: 1. Relocation of 4 units of rotten pole (AGMA Priority) at Sitio Muhon, Barangay Rosario, Dumalag 2. Conversion of lines from V-phase to three-phase at Barangay...
POST EMERGENCY POWER INTERRUPTION REPORT
Reason: Emergency repair of damaged Blade Disconnection Switch caused by animal intrusion. Areas Affected: Feeder 2: Municipality of Pontevedra, portion of Panitan and portion of Panay Feeder 3: Brgy. Timpas, Panitan , portion of Sigma and portion of...
POST SCHEDULED POWER INTERRUPTION REPORT
From 8:30 AM to 5:00 PM Affected Areas: • Barangay Mangoso. Sitio Maralusan, Atiplo, Mambusao. • Barangay Balacuan, Matinabus, Mansacul and portion of Guintas, Sigma Accomplished: Line maintenance and line clearing operation Working Crews: #TeamMAOMaintenance Team...
MEMBER-CONSUMER-OWNER REQUEST ACTED
Calapawan, Panay Rehabilitation of kilowatt hour meters Working Crew: #TeamCAPELCOTaskForce Isuzu 2 Team Members: M Nain, E Cainday, E Delos Santos and G Datar
POST EMERGENCY POWER INTERRUPTION REPORT
Areas affected: • Barangays Bolo, Lanot, Cabugao, Jumaguicjic, San Jose and Lonoy, Roxas City and the • Municipality of Ivisan Reason: Damaged suspension insulator at Barangay Lonoy, Roxas City Responding crew: #TeamRCAOMaintenance Linemen: P Declaro, P Bolinas and R...
POST SCHEDULED POWER INTERRUPTION REPORT
From 6:00 AM to 3:00 PM Areas affected: • Barangay Cabugcabug, Badiangon, Bayuyan, Sto. Niño, Carmencita, Goce and Manoling, President Roxas. • Barangay Yating, San Silvestre and Tabun-acan, Pilar. Accomplished: Conversion of line from V-phase to 3-phase and line...
CONSOLIDATED TEAM ACCOMPLISHMENT BT11
#TeamBobongSaron BT 11 Team Members: J Saron, R Fabella, M Batuampo and M Deocampo Accomplished: 1. Relocation of pole at Barangay Mianay, Ivisan 2. Correction of service drop wires and telcos wire at Barangay Dayao, Roxas...
WEEKLY AND CONSOLIDATED TEAM ACCOMPLISHMENTS BT 10
#TeamGeraldCondino BT 10 Team Members: G Condino, C Daliva, NM Distura, M Umiten and A Ordas Accomplished: 1. Assisted during the power interruption from Bonga, Mambusao to Linambasan, Jamindan o Relocation/conversion of pole from C-4 to C-15 o Replacement of polymer...
SCHEDULED POWER INTERRUPTION
1. ABRIL 25, 2024 (Huwebes nga adlaw) 8:30 sang aga tubtob 5:00 sang hapon Ang CAPELCO magapatigayon sang Line Maintenance kag Clearing. LUGAR NGA APEKTADO: -Brgy. Matagnop, Malonoy, Agtanguay, Daplas, Ilas Sur, Ilas Norte kag Centro, Dao. 2. ABRIL 26, 2024 (Biyernes...
AREA OFFICE MAINTENANCE ACTIVITY
Dumalag Area Office Various Dates Accomplished: Rehabilitation of metering in the following barangays • Lagdungan, Tapaz • Duran, Dumalag • San Roque Proper, San Roque 1, Dumalag • Poblacion Ilawod, Dumalag Working Crew: #TeamDUMAOMaintenance Team Members: M Antonio,...