JOINT TEAM ACCOMPLISHMENTS BT2 AND BT7
#TeamKennyCordovero BT2 Team Members: K Cordovero, A Ferrer and R Distura #TeamRamilDistura BT7 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog Accomplished: Pull out of poles and rehabilitation of kilowatt hour meters at Barangay Parian,...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT9
#TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura Accomplished: 1. Installation of 25KVA rental transformer at Barangay Pangabuan, Jamindan 2. Pull out of 50 KVA transformer at Municipality of Jamindan 3. Pull out of 15...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT1
#TeamTamtamDangan BT1 Team Members: A Dangan, R Daliva, J Penuela, J Degones and PP Fuentes Accomplished: 1. Pull out of idle 15 KVA transformer at San Vicente, Tapaz 2. Pull out of idle materials and transfer kilowatt hour meters at Sitio Ulilik, Barangay Sta. Ana,...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 7
#TeamRamilDistura BT7 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog Accomplished: Pull out of pole and idle materials and transfer of metering from Barangay Agsilab to Barangay Lonoy, Sapian
EMERGENCY POWER INTERRUPTION
Vehicular accident at Ongol Dumarao The construction crew is on the way but this means that Dao, Cuartero and Dumarao will lost power until the trouble with the line is fixed.
ENERGIZATION OF RELOCATION SHELTERS FOR THE FIRE VICTIMS
Tanza Ville Resettlement Project, Tanza, Roxas City As of today, a total of 104 units have been energized at Tanza Ville designated by the Roxas City as relocation shelters for the fire victims at Barangay VII. A team of CAPELCO personnel provided service drop...
SCHEDULED POWER INTERRUPTION
8:30 sang aga tubtob 4:30 sang haponAng CAPELCO mapatigayon sang Line Maintenance kag Clearing.1. MARSO 6, 2024 (Miyerkules nga adlaw)LUGAR NGA APEKTADO:-Brgy. San Rafael, San Martin, San Agustin kag poryson sang San Roque, Dumalag2. MARSO 7, 2024 (Huwebes nga...
WEEKLY AND CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8
#TeamGeraldCondino BT 8 Team Members: G Condino, C Daliva, NM Distura, M Umiten and A Ordas Accomplished: 1. Continued grounding installation Feeder 8-R Pueblo de Panay line section, Lawaan to Dinginan, Roxas City 2. Rehabilitation of lines due to fire incident at...
POWER RESTORATION UPDATE
As of 12:26 AM, March 2, 2024 power to all feeders lines have been restored. Power in Capiz FULLY RESTORED.
EMERGENCY POWER INTERRUPTION
UPDATE: ANG BILOG NGA ISLA SANG PANAY, NEGROS KAG GUIMARAS ANG APEKTADO SINING MALAPNAGON NGA BROWNOUT. ANG RASON AMO ANG PAG TRIP OFF SANG GENERATOR SANG PEDC.With the exception of Pontevedra, portion of Panitan, Panay and Sigma, Capiz is currently out of power....