CONSOLIDATED TEAM ACCOMPLISHMENT BT9
April 20 and April 23-24, 2024, Friday, Tuesday and Wednesday #TeamHonepherDelfin BT9 Team Members: H Delfin, RV Fadirugao, A Daliva, MA Bolinas and F Distura Accomplished: 1. Installation of 50 KVA temporary transformer at Barangay Aglalana, Dumarao 2. Replacement of...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8
April 23-24, 2024, Tuesday to Wednesday #TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog Accomplished: 1. Relocation of 4 units of rotten pole (AGMA Priority) at Sitio Muhon, Barangay Rosario, Dumalag 2. Conversion of lines...
POST EMERGENCY POWER INTERRUPTION REPORT
April 25, 2024 11:07 am to 11:28 am Reason: Emergency repair of damaged Blade Disconnection Switch caused by animal intrusion. Areas Affected: Feeder 2: Municipality of Pontevedra, portion of Panitan and portion of Panay Feeder 3: Brgy. Timpas, Panitan , portion of...
POST SCHEDULED POWER INTERRUPTION REPORT
April 24, 2024, Wednesday From 8:30 AM to 5:00 PM Affected Areas: • Barangay Mangoso. Sitio Maralusan, Atiplo, Mambusao. • Barangay Balacuan, Matinabus, Mansacul and portion of Guintas, Sigma Accomplished: Line maintenance and line clearing operation Working Crews:...