POST SCHEDULED POWER INTERRUPTION REPORT

POST SCHEDULED POWER INTERRUPTION REPORT

July 9, 2024, Tuesday As scheduled: From 4:00 AM to 8:00 AM Reason: NGCP’S De-energization of CAPELCO Feeders (69KV Panitan-Roxas Transmission Line and Timpas Transformer TR1) to facilitate hotspot correction Areas affected: • Whole of Roxas City except Barangay...
MEMBER-CONSUMER-OWNERS REQUEST ACTED

MEMBER-CONSUMER-OWNERS REQUEST ACTED

July 6, 2024, Saturday Tinaytayan, Dumarao Accomplished: Replacement of rotten pole July 6, 2024, Saturday Calanza Street, Poblacion Tacas, Cuartero Accomplished: Relocation of pole Working Crew: #TeamTamtamDangan BT7 Team Members: A Dangan, R Daliva, R Daliva, JP...
CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 8

July 1-5, 2024, Monday to Friday #TeamRamilDistura BT8 Team Members: R Distura, R Sombilla, J Arroyo, J Doce and R Parohinog Accomplished: 1. Continued digging and installation of down guy wire for new line (relocation of 3-phase line) at Barangay San Esteban, Pilar...