POST EMERGENCY POWER INTERUPTION REPORT
September 5, 2024, Thursday Time 5R: From 2:54 PM to 3:14 PM Reason: Disconnected primary line (roadside) in front of Governor’s Mansion, ESLA, Lanot Roxas City Areas affected: Barangay Bolo, Lanot, Cabugao, Jumaguicjic, San Jose and Lonoy, Roxas City Responding Crew:...

SCHEDULED EMERGENCY POWER INTERRUPTION
Sityembre 6, 2024, (Biyernes nga adlaw)Alas 5:00 tubtob 6:00 sang agaAng CAPELCO magapatigayon sang replacement of insulatorApektado nga Lugar: Portion sang Brgy. Lawaan, Arcabalo Bolo, Crossing Jail, St. Ignatius Valley Subd., Wilcon Depot, City Hardwares, Triumph...

SCHEDULED POWER INTERRUPTION
Sityembre 7, 2024, (Sabado nga adlaw)Alas 8:00 sang aga tubtob alas 4:00 sang haponAng CAPELCO magapatigayon sang Upgrading of Lines angot sa DPWH Road Widening Project.Apektado nga Lugar:-Portion sang Barangay Bailan,-Kabarangayan sang Ilawod, Ilaya, Tacas, Malag-it,...

SEMA BENEFICIARIES UNDERWENT PRE-MEMBERSHIP ORIENTATION SEMINAR (PMOS)
September 4, 2024, Barangay Liong and Barangay Milibili, Roxas City The roll-out of the implementation of the Socialized Energization of Marginalized Applicants (SEMA) for Electric Service Connection continues as two more barangays underwent Pre-membership Orientation...

POST EMERGENCY POWER INTERUPTION REPORT
September 4, 2024, Wednesday A series of major power interruptions occurred in the second district affecting the Municipality of Dao, Sapian and portion of Mambusao and Tapaz occurred yesterday until the early morning today due to intrusion of animals into the...

POST EMERGENCY POWER INTERRUPTION REPORT
September 4, 2024, Wednesday 4:16 PM to 4:50 PM Areas affected: Municipalities of Pilar, President Roxas, Maayon, Panay, portion of Pontevedra, Panitan and Barangays Adlawan, Liong, Loctugan, Bago and Olotayan, Roxas City Cause: Disconnected primary line that got...

SEMA BENEFICIARIES UNDERWENT PRE-MEMBERSHIP ORIENTATION SEMINAR (PMOS)
September 3, 2024, Barangay Cabugao and Barangay Dinginan, Roxas City As CAPELCO builds on the initial success of the implementation of the Socialized Energization of Marginalized Applicants (SEMA) for Electric Service Connection, it conducted a series of...

SCHEDULED POWER INTERRUPTION
Ang CAPELCO magapatigayon sang Line Clearing & Maintenance 1. Sityembre 5, 2024, (Huwebes nga adlaw) Alas 8:00 sang aga tubtob alas 4:30 sang hapon Apektado nga Lugar: - Brgy. Liong, Crossing Adlawan (portion), Jumaguicjic(portion), Roxas City - Brgy. Ilas Norte,...

POST SCHEDULED EMERGENCY POWER INTERRUPTION REPORT
September 3, 2024, Tuesday As scheduled: From 5:00 AM to 6:00 AM In Actual: From 5:00 AM to 5:57 AM Accomplished: Correction of line including replacement of damaged insulators Areas affected: FEEDER 4R AND 6R – Plaridel St. TATC,Gaisano Market, St. Anthony Hospital,...

CONSOLIDATED TEAM ACCOMPLISHMENTS BT 7
August 27-28 and 30-31, 2024 and September 1, 2024, Tuesday to Wednesday, Friday to Sunday #TeamTamtamDangan BT7 Team Members: A Dangan, R Daliva, R Daliva, JP Hachuela and PP Fuentes Accomplished: 1. Secondary line extension at Poblacion Ilaya, Panitan (paid project)...